The project will comprise the following:
- Ground Floor - Central Sterile Supply Department (CSSD)
- First Floor - Theatres and Critical Care
- Second Floor - Theatres and Critical Care support accommodation
- Third Floor – Laboratories
The areas listed below have progressed and many will continue during the forthcoming months.
- Level 1 slab is now complete
- Final pour to level 2 will happen this week
- Areas of level 3 slab have now been poured
- Columns are progressing, level 2 to level 3
- Drainage is now complete
- External walls are progressing to levels 0, 1 and 2
- Internal f/faced block walls are being built to level 1 plant room areas
- Site sign board erected
- Equipment procurement meetings underway