16 Jan 08 - Ulster Hospital Critical Care Complex – Construction Update |

16 January 2008
Ulster Hospital Critical Care Complex – Construction Update
Welcome to the Seventh update for the Ulster Hospitals Critical Care Complex where you will find updated images on the preparation works and construction of the building.

Artists Impression of the new Critical Care Complex
|
The project will comprise the following:
- Ground Floor - Central Sterile Supply Department (CSSD)
- First Floor - Theatres and Critical Care
- Second Floor - Theatres and Critical Care support accommodation
- Third Floor – Laboratories
The areas listed below have progressed and many will continue during the forthcoming months.
- Floor slab to level 0 is now complete
- Retaining walls are now 90% complete
- Level 1 slab is progressing ahead of level 2
- Level 2 slab continues to be poured on programme
- Columns are progressing from level 2 to level 3
- Drainage is continuing under the area in front of the site offices
- Foundations for the site sign board have now been completed
For more information on construction work in the Ulster Hospital and the New Downe Hospital please click here. |